My supplier's dates keep slipping

Measuring lead time as a distribution, deciding between stock and safety lead time, and scoring the supplier.

The quote says 30 days. The last three deliveries were 41, 52 and 38. You pad every order by a fortnight and still get caught.

Short answer

Stop treating lead time as a number and treat it as a distribution. Record every delivery against its order date, compute the mean and the spread, and then decide whether to cover the spread with stock or with a safety lead time. If the supplier is consistently late rather than variable, a padded order date may be cheaper than more stock.

Why padding fails

A pad built from memory is neither the mean nor the tail; it is a hope. It also hides the problem from the arithmetic: you pay for extra days of stock whether or not the delivery is late, and you never learn whether the supplier is improving. Measuring the spread lets you compare the cost of holding buffer stock against the cost of ordering earlier.

The fix, in order

  1. Log every delivery: order date, promised date, actual date.
  2. Compute mean and standard deviation of the actual span. With few deliveries, state the uncertainty; eight deliveries give a wide band.
  3. Separate the stages if you can: production, origin dwell, transit, customs, drayage. The stage with the variance is the one to fix.
  4. Choose the lever: stock for demand uncertainty, time for supply timing, capacity for supplier throughput.
  5. Score the supplier on on-time-in-full and on the spread, not on the relationship.
  6. Re-measure quarterly. A supplier that improves should earn a smaller buffer.

When it is something else

If lateness is seasonal, the mechanism is congestion, not the supplier's baseline. If one SKU is always late and others are not, it is a production or material issue. If the supplier is late only when you order small, MOQ or scheduling is the cause.

Next: measuring lead time · safety lead time · supplier scorecards