S5 · practical decision
Supplier scorecards that change a decision
A four-metric supplier score with explicit pass lines, so moving volume becomes an argument backed by your own delivery records instead of a memory of the last late order.
Which supplier is worse, and by how much? Without a scorecard the answer is whichever one was late most recently, and the decision that follows is a mood rather than an argument. A scorecard exists to turn that into two numbers and a policy: this supplier is at 50% on-time-in-full, the policy says formal review below 70%, therefore the review opens.
The test of a scorecard is not whether it is comprehensive. It is whether each line on it can change something you do. A metric you would not act on is decoration, and it dilutes the metrics you would.
Four metrics, and what each one moves
On-time-in-full (OTIF). The share of purchase order lines that arrived complete and inside the delivery window you agreed. This is the only score that feeds your buffer arithmetic, because lateness and short-shipping are the two ways supply actually fails. Define the window explicitly: "on or before the promised date" is a harsher and more useful window than "within ±7 days", and if you use a tolerance band you must say so, or two people comparing scores will be measuring different things.
Lead-time mean and spread. The supplier's arrival pattern: mean span and standard deviation, computed as in lead-time measurement. Report these as two separate lines, never one. A mean that creeps upward is a planning problem you can absorb by re-timing the reorder point. A spread that widens is a buffer problem with no cheap fix — the safety stock has to grow or the supplier has to go.
Unit accuracy. Units received against units ordered, and correct SKUs against the ASN or packing list. This is the upstream half of record accuracy: a supplier who substitutes a variant or ships 272 instead of 296 creates a Shopify discrepancy that someone will spend an afternoon chasing and may mis-diagnose as a receiving error.
Commercial flexibility. Willingness to move on MOQ, to hold your production slot at peak, to give notice of a price change, and to extend terms. Score the artifact, not the relationship: did they answer the capacity question by the date they said, and did the last price change arrive before you had committed the season's buy?
Deliberately absent: "communication" and "partnership". Neither is measurable from records, and both become a way of letting a supplier you like pass a scorecard they should fail.
The worked score
Marlow & Finch buys MUG-GRN-12 from an overseas ceramics supplier on a quoted 45 days, and its notebooks and gift boxes from a domestic printer on about six days. Eight ceramics deliveries, measured from PO sent to stock available:
| Span (days) | 52 | 39 | 49.5 | 41 | 48 | 42 | 43.5 | 45 |
Mean 45.0, sample standard deviation 4.5. The delivery that landed on day 45 also arrived 24 units short on a 296-unit order.
- On time (arrived on or before day 45): 39, 41, 42, 43.5, 45 → 5 of 8 = 63%
- In full: 7 of 8 → 88%
- OTIF: both conditions on the same delivery → 4 of 8 = 50%
Note that 63% × 88% = 55%, not 50%. OTIF is not the product of its two components, because the failures overlap — the short delivery was also borderline on time. Reporting OTIF as an independent count is the only way to avoid flattering a supplier whose bad luck clusters.
The domestic printer over twelve deliveries: mean 6.2 days, σ_L 1.1, on time 11 of 12, in full 12 of 12, OTIF 92%.
The policy. These lines are Marlow & Finch's own rule, set by the owner, not an industry norm. Above 90% OTIF: no action. 70–90%: note it, watch the trend, do not change volume. Below 70% on two consecutive quarters: formal review, with the supplier present. Below 60%: qualify an alternate source in parallel.
The decision. At 50% the ceramics supplier is below every line at once, and the answer is not "complain harder". It is: open the review, and begin qualifying a second source — which is where dual sourcing starts, and where most of the difficulty lives. The commercial consequence of the 24-unit short is small in margin ($197 at the $8.20 unit margin) and larger in cover: 24 units is 3.4 days of demand at 7.08 units a day, which will produce a visible gap if the next container is on the late side of its own distribution. The printer needs nothing.
Two things the score cannot tell you
Why. A widening spread and a drifting mean look identical in a score table and have opposite remedies. Split the span into milestones — PO to ex-factory, ex-factory to port, port to port, port to door — and the variance usually concentrates in one of them, as importing and freight sets out. Score the total; diagnose the parts.
Whether you can leave. A scorecard on a single-source supplier with no qualified alternative is a document about your own exposure, not a lever. Score it anyway, and treat a bad score there as a mandate to build the alternative rather than to negotiate.
Where this breaks
Eight deliveries cannot distinguish a supplier with σ_L of 4.5 from one with σ_L of 8; the lead-time measurement lesson puts the honest 90% band on that estimate and it is wide. Do not run a review meeting on a confidence interval that wide — run it on the OTIF count, which is far more robust at small n.
A supplier can game OTIF upward by quoting a longer promise. A score of 100% on a 60-day quote is worse than 80% on a 45-day one for your cash, and only the mean/σ lines catch it. Score per PO line rather than per shipment, or one late line in a forty-line container will report the whole container as late and swamp the signal. And never carry a scorecard on price alone: the cheapest quote with a 4.5-day spread is frequently the most expensive supply option once the buffer it forces you to hold is priced at carrying cost.
Assumptions
- Deliveries are the unit of observation and each PO line's span is independent of the others. In practice a shared container correlates them; eight deliveries of one container per month are closer to eight observations of one supply process than eight independent draws.
- "On time" means on or before the promised date, with the promise recorded at PO confirmation, not reconstructed afterwards.
- Recorded receipt date is the date stock became available to sell, not the date it arrived at the dock.
- The 45-day mean and 4.5-day spread are the running example's figures, taken as given for the worked score rather than re-derived here.
- OTIF counts treat each PO line as equally important; it does not weight by margin or velocity.