Chapter 4 · conceptual understanding
Replenishment and lot sizing
The two decisions every purchase order makes — when to place it and how much to put on it — and why the second one is harder than the formula suggests.
Every purchase order answers two questions, and they are not the same question. When do I place it? How much goes on it?
Marlow & Finch's green mug answers the first one with a number: 384 units. When the inventory position — on hand, plus anything already on order, minus anything backordered — falls to 384, the order goes in. That number is the lead-time demand you expect to sell while waiting (319) plus the buffer you decided to hold because the wait is uncertain (65).
The second question gets 296 units, an economic order quantity. It is the point where a year of ordering costs plus a year of holding costs is at its minimum: 5.4 orders a year at $35, plus an average cycle stock of 148 units at $1.28.
Two decisions, two numbers, 384 and 296. Both are wrong the moment the regime, the pack size, or the supplier's terms differ from what the arithmetic assumed — and unlike most wrong numbers in inventory, these fail quietly. You do not get a stockout the day you set a reorder point three days too low. You get one in seven weeks, on a Tuesday, and it looks like a demand spike.
What this chapter is protecting you from
A reorder point that ignores lead-time variability. On the mug, 65 of the 384 units exist because the ceramics supplier's timing moves. Drop that term and the reorder point computes to 319 + 39 = 358, twenty-six units short, and the buffer is understated by 41%. This is the single most common error in reorder-point arithmetic and it produces a system that looks disciplined and runs out regularly.
EOQ treated as robust to everything. It is startlingly robust to parameter error — a fourfold mistake in ordering cost only doubles Q, and ordering at twice the EOQ raises cost by just 25%. It is fragile to structural error: an MOQ, a quantity break, or a case pack changes the problem, not the inputs, and the formula has nothing to say about it. A merchant who has learned "EOQ is forgiving" and stopped there is holding the wrong lesson.
Min, max and reorder point used interchangeably. They are three different numbers serving two different regimes, and a stack that offers all three as free-text fields does not stop you from entering an incoherent set. Min 384 with max 477 orders 93 units every time, a third of the economic quantity and 75% more in ordering and holding cost. Both numbers look defensible in isolation.
MOQ silently over-ordering. The supplier's minimum is not a constraint you meet; it is a constraint that redefines what an order is. A 500-unit minimum on a SKU whose economic quantity is 91 does not cost you a rounding difference. It costs you two years of stock and a markdown.
The four lessons
- Reorder point — how 319 + 65 becomes 384, what "position" means, and why on-hand is the wrong field to compare against.
- Min-max versus order-up-to — the two coherent ways to set a min and a max, and the incoherent way that most stores end up with.
- Lot sizing beyond EOQ — period order quantity, Silver-Meal and least-unit-cost, with Wagner-Whitin named as the exact method and quantity breaks handled properly.
- MOQ and pack integrity — case packs, inner packs and minimums as decision constraints, and the thresholds for when rounding is harmless and when it dominates.
What you need before starting
This chapter assumes two things you should have already. First, a demand rate you trust — 7.08 units a day on in-stock days, not the sixteen-month average that includes the period the mug was dark. That is Measuring velocity, and every number here inherits its errors. Second, a buffer sized deliberately rather than picked, which is Sizing safety stock from variance. If the buffer is a guess, the reorder point is a guess with better formatting.
Where this stops
The whole apparatus assumes the supplier will accept whatever order you send, whenever you send it, at a unit cost that does not change with quantity. None of those three is true of a real ceramics supplier: there are minimums, there are case packs, there are price breaks at volume, and there are terms that shift the cash timing without touching the inventory at all. The lot-sizing lessons name these as structural breakers rather than treating them as noise.
It also assumes the lead time is a single number. Where a supplier ships in partials, or the freight consolidator holds a container for a week, the "lead time" is a composite and the reorder point built on it is an average of things that do not average well — which is Measuring lead time from your own deliveries's territory.
Lessons in this chapter
Computing a reorder point
Turn a demand rate, a lead time and a buffer into the single number that triggers a purchase order.
quantitative skill·6 min read
Min-max versus order-up-to
How to choose the two numbers in a min-max pair so the gap between them is your order quantity rather than an accident.
practical decision·6 min read
Lot sizing beyond EOQ
Period order quantity, Silver-Meal and least-unit-cost, plus why quantity breaks and MOQs break EOQ rather than adjust it.
quantitative skill·6 min read
MOQs and pack integrity
How case packs, inner packs and minimums silently rewrite the order quantity, and the thresholds for when that is harmless.
practical decision·6 min read