Where the 45 days actually go
Decomposing an imported lead time into queue, production, transit and clearance, and why the variable part is the part you cannot see from the tracking number.
Prerequisites
The ship takes three weeks. Why does the order take 45 days to arrive?
Because the ship is the smallest part of the problem and the only part that is visible. Between sending a purchase order and putting mugs on a shelf there are seven or eight stages, each with its own mean and spread, and the tracking number only starts reporting from the fourth one. A merchant who plans against the transit time has planned against the stage that almost never moves.
The decomposition
Here is MUG-GRN-12's 45 days taken apart. The figures are Marlow & Finch's own illustrative build for this supplier, not an industry schedule.
| Stage | Mean days | What moves it |
|---|---|---|
| Queue for a production slot | 6 | The factory's order book when your PO lands |
| Production run | 5 | Kiln scheduling, glaze batches, rejects |
| Ex-factory to port, booking | 3 | Truck availability, cut-off dates |
| Dwell at origin port | 4 | Sailing schedule, missed cut-off |
| Ocean transit | 20 | Route, service speed, transhipment |
| Dwell at destination, customs | 4 | Document errors, inspection flags |
| Drayage and receiving | 3 | 3PL appointment backlog |
| Total | 45 |
Two things follow immediately from this table.
The transit is not the lead time. Twenty of 45 days are on the water. If you shortened the crossing to ten days — a faster service, at a price — you would take 30 days off nothing, because the queue, the run and the dwell would still be there. This is why air freight so often disappoints: it compresses the one stage that was already short and leaves the queue untouched.
The queue is the variable stage. A crossing has a narrow distribution; a factory order book does not. You do not have a slot until the factory's existing commitments clear, and where your order falls in that book is decided by the date you placed it, not by anything you control afterwards. The queue is therefore both the largest source of spread and the one that responds to nothing you can buy at the port.
Why the queue is where the variance lives
Put numbers on it. Suppose the queue varies with a standard deviation of 4 days and every other stage combined varies with a standard deviation of 2 days. Variances add for independent stages:
σ_L = √(4² + 2²) = √20 = 4.47 days
which is the 4.5 the running example uses. The queue contributes 16 of the 20 units of variance — 80% of the uncertainty, from a stage that appears nowhere in the freight documents and takes zero days in the supplier's quotation.
This is the mechanism the chapter keeps returning to. Your lead time is a position in someone else's production queue plus a fairly predictable journey. It is not a delivery service level, and it does not improve because a shipment moved fast. It improves when you order earlier relative to the queue or book capacity in advance.
The practical consequence is that lead-time measurement is only half the job. A single 45-day number is a blend of eight processes, and a blended σ_L tells you the buffer you need but not what to fix. Record milestones — the slot confirmation, the ex-factory date, the sailing date, the arrival date — and the variance separates. If 80% of it sits in the queue, a deposit to hold capacity reduces σ_L in a way no forwarder negotiation can.
The landed cost is also a build
MUG-GRN-12's $5.80 is not a supplier price. It is a sum: FOB $4.60, ocean freight $0.62, duty $0.35 (7.6% of FOB at this merchant's illustrative rate), brokerage and cargo insurance $0.23.
Each line behaves differently under a decision. Freight is largely fixed per container, so its per-unit cost falls as you fill the box — the real reason an MOQ exists, as payment terms and MOQ sets out. Duty scales with value. And because landed cost is the base for the 22% carrying cost, the $0.62 freight line adds $0.14 a unit a year to the cost of holding: freight is paid once and carried forever.
Who owns the goods while they float
On FOB-origin terms, you own the mugs from the moment they are loaded at the origin port — roughly day 14 of the 45. From that day they are your inventory: your capital is in them, they are a line in your cash conversion cycle, and they are exposed to damage and obsolescence. On a DDP or destination term the supplier owns them until they clear, and the same 45 days consume no working capital until day 42.
The stock is identical; the cash consequence differs by about a month of purchases, permanently. And note the asymmetry the carrying cost lesson insists on: goods in transit consume no rent, so the 6% rent share of the 22% rate does not apply to them — but the 5% capital and 7% obsolescence components do. Applying the full 22% to pipeline stock overstates it; applying zero understates it badly.
The container that slips at peak
The named failure for this lesson. A container ordered for a Q4 peak arrives well after the peak: the queue lengthened because every other buyer placed their peak order in the same window, and the transit did not change at all. Nothing went wrong with the shipping. The lead time went to 70 days because the queue went to 30.
The failure is not the delay. It is that the plan treated 45 days as a property of the supplier rather than a property of the date the order was placed. Peak-season lead time is a different distribution, with a longer mean and a wider spread, and averaging the two produces a plan wrong in both directions — too much buffer in March, none in November.
The repair is to measure the peak separately: keep two histories, or add a calendar term to the buffer for months where the queue habitually lengthens. That is far cheaper than lifting σ_L for the whole year, which funds a peak-sized buffer in every month.
Where this breaks
The decomposition assumes stages are independent. They are not: a missed port cut-off is often caused by a late production run, and a customs inspection is more likely on a shipment whose documents the forwarder rushed. Correlated stages mean the total spread is larger than the sum of independent variances suggests, and the model understates the tail precisely in the bad months.
The build also assumes one shipment per order. With a 3PL plus a back room you have two echelons and a question about where stock sits — the useful part of which is pooling, covered in Why pooling beats splitting. Full multi-echelon optimisation is deliberately out of scope: two locations and one forwarder is not a distribution network, and a merchant at this scale does not have the problem.
Finally, none of this survives a change of terms mid-relationship. Moving from FOB to DDP changes who carries the transit risk, and the σ_L measured under one term is not the σ_L you get under the other.
Assumptions
- The stage means are an illustrative build for this merchant, constructed to sum to the running example's 45 days. They are not measured industry figures.
- Stage durations are independent and roughly normal, so their variances add. Correlated stages are treated in "Where this breaks".
- The stage means are stationary across the year, which the peak section explicitly contradicts — that is why the peak is measured as its own distribution.
- Demand during the span is stationary at d̄ = 7.08 units a day and independent of the queue length.
- Duty, freight and insurance are illustrative per-unit allocations, not quotations.
- In-transit holding applies capital and obsolescence only (12%), on FOB-origin terms.