4 total- 16-22 week lead times and one human babysitting 400 line items
@ruth t you can probably build it in excel. current on hand minus allocated, projected demand decrementing weekly, inbound pos adding, and you get a…
- 16-22 week lead times and one human babysitting 400 line items
@ruth t that's one i don't know well. buying more often might help — negotiate lower moq, maybe they'll hold a little stock for you. otherwise focus…
- 16-22 week lead times and one human babysitting 400 line items
@ruth t what's the product? nine times out of ten it's the same excuse and it only really holds one time in nine.
- 16-22 week lead times and one human babysitting 400 line items
the real options are carry more safety stock to cover lead-time variance, get a better forecast (needs solid input from sales and that's hard), or…