the item master says 21 days. the last six deliveries took 45 to 70.

noor_nPosted

serious question.

we're a small specialty food producer in new south wales, about 300k a year, marketplace plus our own site. one imported ingredient is set to 21 days lead time in the item master. the supplier's last six deliveries came in somewhere between 45 and 70. which number does your team actually plan against?

for us that gap is the entire difference between a purchase order going out and the production line standing still with three staff on the clock.

so do you use goods receipt history to push back on the supplier's lead time, or does everyone just keep running the stored value until something blows up?

18 replies

  1. b_webb

    these have to be reviewed on a schedule. and the person doing it might be carrying thousands of lines, so it's easy to see why one gets stale. sounds like you've zeroed in on one. have you asked whoever owns the master to correct it?

  2. chris_merch

    @b_webb

    this. op's one ingredient was late and now the whole system is the villain

  3. n_okafor

    @b_webb

    also worth saying a lot of food inputs still have lead time problems depending on origin. a fair few categories never really went back to normal.

  4. tomasz_logistics

    @noor_n

    then put a number on it and take it to whoever signs the cheques. "nine thousand in extra stock versus four days of stoppage" is a sentence that gets a decision. "we should update the master" is a sentence that gets a meeting.

  5. rob_49

    we planned against either a predicted lead time or the contracted one, depending on how many orders we'd had for the item. ideally procurement keeps it current, but as others have said, the number of lines per buyer is enormous.

    related, planning this kind of inventory was one of the more stressful jobs i've had. thousands of lines and locations per planner, ancient systems, plenty of items that move less than once a year anywhere, and a huge impact when demand shows up and the shelf is empty.

  6. laura_25

    @rob_49

    and when you use recent history you overbuy once the supplier problem gets fixed. bullwhip. always fun standing in front of empty shelves because of late pos while someone upstairs yells to cut more pos.

  7. copperline

    the first half of this is supplier management. a 21 day promise and a 70 day reality is an unacceptable gap from what was agreed. whether it's temporary or the new normal is a call the buyers and the owners have to make between themselves. it should hit sourcing decisions and the supplier rating.

  8. maya_51

    there should be periodic reviews and the records updated as new information arrives. and somebody should be able to answer how 21 days got in there in the first place.

  9. kieran_sourcing

    good luck with that at scale. you need multiple parties not just on board but compliant, and staying compliant afterwards. as the first reply said, it's supplier management and it's not acceptable, but i see it constantly. you need top management behind it or it dies. and lead times change, so it needs updating forever, which is never something you can just automate. buyers have to care.

    uphill battle. good luck.

  10. katie_89

    we don't even populate lead times for a lot of our low-value lines. waste of time the way supply chains have gone. with thousands of skus you pray they hit it and keep enough minimum on the shelf.

  11. tomasz_logistics

    wouldn't trust either number on its own. the master tells me what we planned. receipts tell me what actually happened. if it says 21 and the last six came in at 45-70, i'm planning around the actual and asking why the master hasn't caught up.

    i'd go past the average though. look at the spread. 58 average ranging 50-65 is a different animal from 58 ranging 30-95.

    the bigger issue is ownership. who reviews actual lead time and updates the planning parameters? if the answer is nobody, the master is just a pile of old assumptions. systems don't make good planning data. processes do.

  12. jules_71

    because sales is running a config with the old lead times. silos keep it alive.

  13. shelfside

    my erp has a separate internal receipt processing time so i can add a logistics buffer on top of the supplier lead time. have to babysit it though, or it quietly becomes another lie.

  14. sinead_52

    @tomasz_logistics

    the spread is the bit people skip. an average is useless if the range is 30-95. safety stock has to cover the bad end, not the middle.

  15. c_brennan

    sorry, basic question — what's the actual harm in just setting it to 70 and being done with it? surely too much lead time is safer than too little?

  16. tomasz_logistics

    @c_brennan

    it is safer for service and worse for cash. 70 days of cover on a $9 ingredient across a few pallets is real money tied up, and if the real lead time comes back to 40 you're now carrying a month of stock you don't need. the buffer isn't free, it's just usually cheaper than a stoppage. usually.

  17. gabe_planning

    coming back to this because we just did the exercise. the thing that finally moved it wasn't the planner, it was the accounts person noticing how much we'd spent on expedited freight over two quarters. money talks in a way that "the master is wrong" never does.

  18. noor_nOP

    @tomasz_logistics

    ownership is what i keep coming back to. nobody's name is on it. and the cost of the buffer versus the cost of being short should be in dollars, not just argued about in a meeting.