does your production plan survive past wednesday either
i'm the production planner at an outdoor gear outfit in perthshire. we make our own canvas tents, bike-packing bags and a few clothing bits, and we also run two shops and a website. £920kish, 38 people, three sewing cells, a cutting table that is older than me.
my week: sales give me a rough annual number, i turn it into monthly output, check fabric and hardware against orders, build the weekly build plan, decide which cell gets which style, watch the two supervisors, chase trims, and re-plan whenever a shop sells something unexpected or a roll of canvas turns up the wrong shade.
i expected firefighting. i didn't expect the plan to be decorative by wednesday. by thursday we're building whatever has the least missing parts, which is not the same as what sells.
so i'm asking for a baseline, not a moan. what's a normal week for you. how far out can you actually hold a plan. do you own the machine/cell calls or does the floor. is there a supervisor between you and the machinists. what system. and roughly what split of your week is planning, meetings and chasing.
i'll take "it's like that everywhere" as an answer, i'd just like to know if it's true.
19 replies
dan_n where i work those are two jobs. planners plan material and demand, schedulers build the short-term sequence, and manufacturing decides who runs what because they're standing next to the machine.
typical day is chasing parts, fixing bom errors, escalating shortages. plan two to four weeks, no more. machine calls are the supervisors. vacations are hr. sap. and about 35% of my week is meetings, which i think is too many but nobody asked me.
honestly the split exists because one person can't hold all of it. your place sounds like it's asking one person to be three.
matt_merch most of what you listed is the job, though. the split above sounds nice and rare.
two to three weeks, a month at the outside. machine scheduling no. shift planning no. holiday cover no. fires maybe 15% of the day, because we have production managers on the floor.
also sap. one or two meetings a week, half an hour. if a planner is in meetings all day then the setup is wrong, not the planner.
sinead_bOP @matt_merch
one or two a week. i'm sending this to my boss, who has us in a daily 8:30 for forty minutes.
matt_merch @matt_merch
a daily stand-up is fine if it's ten minutes and about today. forty minutes is a planning meeting wearing a lanyard. call it what it is and get it off your calendar.
ben_76 we're a contract upholstery shop and we tried letting the floor choose the machine sequence. it broke. two products can take different routes, so the scheduler was promising dates nobody could hit, then ops blamed scheduling.
we moved the routing call back to whoever owns the promised date. they had to learn the floor and argue with the supervisors, which took six months of unpleasantness, but we hit dates now.
before that the scheduler was also the buyer, which was worse. then we split buying out, and the buyers just put asap on everything. we end up with 85% of a job sitting here three weeks early and one trim from italy holding the whole thing. high stock, nothing buildable.
dan_n @ben_76
i get it, but i still don't want the machine call sitting with someone who isn't on the floor. in my last place i built the schedule in a two-hour block on wednesdays and spent the rest watching for bubbles. production meetings twice a week, which were planning meetings with a different chair.
the scheduling was maybe a quarter of the job. the rest was shortages, bom accuracy with design, maintenance alignment, helping people use sap, and turn times. and no planner has authority. if the floor doesn't follow it, the plan is wrong by definition.
a_webb adjacent rather than the same title. i run fulfilment at a small freeze-dried pet treat company. my week is chasing last week's orders, planning production runs with our co-packer, and whatever project the founder drops on me. there's no clean line between planning and ops here. it's one pile with two names.
tworooms_20 thanks for posting. i thought it was just me.
last company was confectionery, exactly your week. now i'm in medical devices and i feel like a fraud. i raise work orders off orders and forecast, that's the planning. no scheduler, and i'm not allowed to build one because the production manager wants his team to "own their rhythm". so they build what they feel like. they can't see anything outside the four walls, so our own orders go out fine and forecast spikes get missed because there were still a few boxes on the shelf.
i'm supposed to plan the current quarter. i do three because not seeing it has burned me. an hour a day on work orders, the rest is reporting and fires.
yusuf_85 how much you plan versus firefight tracks how often the forecast gets refreshed. annual forecast means you react all year. monthly s&op plus a frozen fortnight and you get to actually plan.
track how often the published weekly plan changes. that's the number for your boss.
sinead_bOP @yusuf_85
it changes most days. sometimes twice. so i have my number, i suppose.
josh_h is it mix changes landing inside your frozen window, or mostly material and bom?
sinead_bOP @josh_h
material and bom. and one cutting table that decides on its own when it wants to run true.
p_iqbal ops director now, was a consultant before. the split depends on company size and maturity. planning follows the sales funnel. machine ownership scales with headcount, maybe one supervisor per fifty. work allocation sits in an hr calendar and feeds availability.
systems: spreadsheet when tiny, then something self-hosted, then the big stuff at six figures before customisation. most of those projects get bungled. if you don't have half a million and two to five people for a year, don't cheap out on an erp. it's change management, not tech.
hugo_62 what
northwind_26 genuine question from someone outside manufacturing: what is a frozen window? is it literally "nobody changes the plan for two weeks", and if so how does that survive a customer ringing up?
yusuf_85 @northwind_26
roughly. inside the window you can change sequence but not the committed volume. outside it, anything goes. the customer call gets handled by whoever owns the promise, not by rewriting the plan five times a day.
kieran_35 we're seasonal (summer tents, winter repairs) and the thing that killed our plan was agency staff. you can plan the cells perfectly and then half the crew on friday is new. we started planning to the slowest person on the cell, which feels defeatist and made the dates real.
not sure that helps. it did make the plan less fictional.
sinead_bOP @kieran_35
actually it does. we've got two people off on friday and i keep pretending the plan is unaffected. it isn't.
palletguy_36 late reply but: nobody has mentioned that your annual forecast is being handed to you as a single number. ask for the range and the assumptions. a number with no range is a wish.
also, if the cutting table is the constraint, plan around the table, not the sewing cells. everyone plans the expensive machines and forgets the one everything queues behind.